Engineering & Public Works COW #01
Mar 23, 2023
Romeyn Stevenson · Solomon Awa · Kyle Sheppard · Swany Amarapala · Ookalik Curley · Simon Nattaq · Paul Quassa · Kimberly Smith · Samuel Tilley
No absence shown in the quarterly grid.
- EPW 23-01 through EPW 23-06 reconcile with the registry. Two unanimous recommendations concerned water-project delivery and AV 305 remediation; agenda, closed-session transitions and adjournment were procedural. The recommendations did not themselves award or direct council work.
- EPW 23-02 recommended changing the Long-Term Water Supply Project delivery approach from design-build to design-bid-build after discussion of design risk, licensing, procurement and community employment. Council issued the direction April 11 under 23-107.
- Staff described limited flow data for the proposed Unnamed Lake source and a future licence application. These were dated planning statements, not evidence of a water licence or completed reservoir.
- The Apex River pumping update described pending electrical and generator work. Staff reported Lake Geraldine near 109 metres and discussed conservation and risks if freshet or supplemental pumping were delayed; these are March 2023 conditions, not current water levels.
- Following a closed session, EPW 23-05 recommended awarding Nunavut Excavating the AV 305 remediation contract. Council recorded a separate award April 11 as 23-108. The minutes do not state a contract amount or establish completion.
Read the City’s documents
This page is an index, not a substitute for the underlying record.