What City Hall said it would do

26 commitments, followed from the vote or statement to the latest public evidence we could identify. An approved budget is not counted as a completed project.

26commitments tracked
4delivered
10partial / on watch
12not publicly verified
Read the status carefully.

“Not publicly verified” does not mean the work was not done. It means the public record reviewed here does not yet prove completion. The City can correct or update any entry with documentation.

October 21 follow-up review

Eight existing entries were updated from October 6 and 20 meeting material and recreation notices. Registration is now marked delivered. Three new follow-ups cover Council documents, Heritage Centre correspondence and the indemnity review. Other entries keep their own earlier review dates.

Issue
Status
Planning · Adopted motion

Investigate the two explosives-storage shelters under LUP 24-004, seek a penalty and report back.

Delivered
On recordJune 18, 2024
Age at review (October 5, 2026)839 days
ResponsibleCity Administration
DeadlineNext available meeting
What the record proves

The July 10 approved Council minutes record the report-back and staff saying a $2,500 fine was issued and immediately paid. Council then approved LUP 24-004 under 24-195.

What remains

No missing report-back is identified. A separate payment receipt or ledger has not been inspected.

July 10, 2024 approved minutes, pages 5 and 6 ↗
Governance · Administration commitment

Provide council with an accessibility report following the November delegation.

Not publicly verified
On recordNovember 28, 2023
Age at review (September 16, 2026)1022 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

The written minutes record that staff would provide a report.

What remains

The report and a recorded council response have not been matched in the indexed public record.

November 28 minutes ↗
Public safety · Administration commitment

Return with information on by-laws and mechanisms for prompt removal of abandoned or crashed vehicles.

Not publicly verified
On recordNovember 28, 2023
Age at review (September 16, 2026)1022 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

Administration agreed to review the available tools and report back.

What remains

The promised report has not been matched in the indexed public record.

November 28 minutes ↗
Public safety · Administration commitment

Present a public-safety plan or program to council.

Partial
On recordNovember 28, 2023
Age at review (September 16, 2026)1022 days
ResponsibleCity Administration
DeadlineLater meeting; no date stated
What the record proves

Council later debated the Public Safety Committee and an internal interagency working group, but that does not by itself establish delivery of the promised plan.

What remains

A clearly identified plan or program matching the commitment remains to be located.

November 28 minutes ↗
Water · Administration commitment

Provide detailed monthly long-term-water reporting and a concise executive summary to council.

Not publicly verified
On recordDecember 12, 2023
Age at review (September 16, 2026)1008 days
ResponsibleLong-term water project team
DeadlineMonthly
What the record proves

The project team said dashboard material was available and accepted monthly reporting in principle.

What remains

A complete public series of monthly executive summaries has not been located in the indexed record.

December 12 minutes ↗
Governance · Administration commitment

Review the scrap-metal contract and determine whether the City receives proceeds from metal sales.

Not publicly verified
On recordFebruary 6, 2024
Age at review (September 16, 2026)953 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

The CAO said he would review the contract terms after Mayor Awa asked whether the City received money from scrap-metal removal.

What remains

A public answer identifying any sale proceeds has not been matched in the indexed record.

February 6 Finance minutes ↗
Governance · Adopted motion

Examine creation of an Outdoor Sports Park Reserve Fund during the budget-amendment process.

Not publicly verified
On recordApril 9, 2024
Age at review (September 16, 2026)890 days
ResponsibleCity Administration
Deadline2024 budget-amendment process
What the record proves

Council adopted Motion 24-91 after removing a proposed $500,000 amount from the direction.

What remains

The final reserve amount and implementation result have not been matched in the indexed record.

April 9 minutes ↗
Governance · Adopted motion

Develop a new recreation-program registration system.

Delivered
On recordSeptember 24, 2024
Age at review (October 21, 2026)757 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

Motion 24-296 directed a new registration system. The March 3, 2026 committee review identifies a lottery-based approach, and the May 12 City notice publishes summer-camp lottery instructions through ActiveNet. A September 2025 notice also describes the lottery for swimming lessons.

What remains

The registration-method change is publicly documented. This does not establish a new software purchase or independently assess fairness and results.

September 24 minutes ↗

March 3 committee review, Recreation section ↗

May 12, 2026 summer-camp lottery instructions ↗

September 2025 swimming-lesson lottery notice ↗

Governance · Administration commitment

Present terms of reference for the new Governance and Priorities Committee at the next council meeting.

Delivered
On recordFebruary 11, 2025
Age at review (September 16, 2026)581 days
ResponsibleCity Administration
DeadlineNext council meeting
What the record proves

Draft terms were presented February 25 and committee appointments were completed March 11.

What remains

No missing delivery is identified for this commitment.

February 11 minutes ↗
Public safety · Administration commitment

Provide council with the Fire Department Needs Assessment requested during the eight-storey housing discussion.

Not publicly verified
On recordApril 8, 2025
Age at review (September 16, 2026)525 days
ResponsibleCity Administration
DeadlineNo deadline stated
What the record proves

The written minutes record Flaherty's request for the assessment.

What remains

Delivery of the assessment to council is not confirmed in the indexed public record.

April 8 minutes ↗
Planning · Staff target

Register the quarry survey within the two-to-three-week timeframe stated by Planning.

Not publicly verified
On recordMay 20, 2025
Age at review (September 16, 2026)483 days
ResponsiblePlanning and Development
DeadlineTwo to three weeks
What the record proves

Planning gave the registration estimate while answering Mayor Awa.

What remains

A registration date or registered survey was not matched in the indexed record.

May 20 minutes ↗
Public safety · Administration commitment

Return with a report explaining low Motor Vehicle Act enforcement numbers.

Not publicly verified
On recordJune 10, 2025
Age at review (October 28, 2026)505 days
ResponsibleRCMP / City liaison
DeadlineNext meeting
What the record proves

The June 2025 promise sought an explanation of low Motor Vehicle Act enforcement numbers. On October 27 police described recent impaired-driving checks, more planned enforcement and highest-offence file scoring. Those are relevant operational updates, but the discussion was not identified as the promised 2025 follow-up report.

What remains

Locate a report explicitly answering the original commitment. Recent enforcement activity alone does not establish that the report was delivered.

June 10 minutes ↗

October 27 Council package and supporting records ↗

October 27 recording, traffic discussion about 14:00 ↗

Roads · Staff target

Address Plateau traffic-calming measures after the planned 2026 paving work.

On watch
On recordSeptember 25, 2025
Age at review (October 21, 2026)391 days
ResponsibleCity Administration
DeadlineOperating plan for 2027
What the record proves

The original commitment ties traffic calming to work after paving. The October 20 capital presentation describes continued Plateau paving proposed for 2027 and 2028. It does not establish delivery of the specific traffic-calming measures.

What remains

Locate the 2027 operating decision, the traffic-calming design and an implementation timetable. Continuing paving alone does not satisfy the safety commitment.

September 25 Finance minutes ↗

October 20 recording, Plateau paving about 50:00 ↗

Governance · Adopted motion

Present regular summary reports from the internal Public Safety Interagency Administrative Working Group to council.

Not publicly verified
On recordJanuary 27, 2026
Age at review (September 16, 2026)231 days
ResponsibleCity Administration
DeadlineNo interval stated
What the record proves

Motion 26-14 makes regular reports part of the approved replacement model.

What remains

No standalone summary under the working group’s name was identified in the public records indexed through August 25.

January 22 minutes ↗
Governance · Administration commitment

Bring a detailed update from each City department to Governance and Priorities every three months.

Partial
On recordMarch 3, 2026
Age at review (October 28, 2026)239 days
ResponsibleCity Administration
DeadlineEvery three months
What the record proves

The public record now includes the May 5 Fire update, September 15 Recreation update (minutes in the October 27 package), October 6 Public Works presentation and October 20 Municipal Enforcement presentation. This establishes further reporting but not a full three-month rotation for every department.

What remains

A department-by-department reporting schedule and evidence of each quarterly return remain to be matched.

March 3 minutes ↗

October 6 package, Public Works presentation ↗

October 20 package, Municipal Enforcement presentation ↗

October 27 Council package and supporting records ↗

Governance · Administration commitment

Create a regular public-engagement route through Governance and Priorities and develop town-hall opportunities.

Partial
On recordMarch 3, 2026
Age at review (October 21, 2026)232 days
ResponsibleCouncil and Administration
DeadlineNo final calendar stated
What the record proves

Public Engagement Items appear in May and October agendas. October 6 includes the Heritage Trust delegation and youth turf correspondence; October 20 includes the College student pool-access request.

What remains

These examples demonstrate use of the agenda route. A complete town-hall calendar and a clear public submission procedure remain to be verified.

May 26 package (includes May 5 minutes) ↗

October 6 public-engagement items ↗

October 20 public-engagement item ↗

Governance · Implementation obligation

Move the subjects and unfinished work of the former committees into the new Governance and Priorities structure.

Not publicly verified
On recordMarch 24, 2026
Age at review (September 16, 2026)175 days
ResponsibleCouncil and Administration
DeadlineNo deadline stated
What the record proves

Motion 26-51 folds the existing committees into Governance and Priorities Committee of the Whole.

What remains

No public crosswalk listing every former committee, its unfinished files and the new reporting location was identified.

March 24 council record ↗
Water · Adopted motion

Complete the Ulu Lane piped-water system at the same time as the piped sewer work using an $860,000 capital amendment.

Not publicly verified
On recordMarch 24, 2026
Age at review (October 28, 2026)218 days
ResponsibleCity Administration
DeadlineNo completion date stated
What the record proves

Motion 26-49 approved the $860,000 water amendment. Council approved the 2027 capital plan as presented on October 27, including the Ulu Lane water-infrastructure allocation. This is later budget authority, not evidence that the physical work is complete.

What remains

A completion record, revised construction schedule and final cost remain unverified.

March 24 council record ↗

October 20 proposed capital plan, Ulu Lane line 16.06 ↗

October 27 Council package and supporting records ↗

October 27 recording, capital-plan approval about 28:15 ↗

Water · Adopted motion

Deliver $3.925 million in Lift Station No. 1 protection and AV205–AV601 sewer upgrades.

Not publicly verified
On recordMarch 24, 2026
Age at review (October 28, 2026)218 days
ResponsibleCity Administration
DeadlineNo completion date stated
What the record proves

Motion 26-47 approved the earlier $3.925-million amendment. Council approved the 2027 capital plan on October 27, including Lift Station No. 1 protection and AV205 to AV601 upgrades. Later budget allocations do not establish delivery of the original scope.

What remains

Match procurement and construction milestones to the original scope, and confirm final costs and completion.

March 24 council record ↗

October 20 proposed capital plan, lines 5.01 and 5.05 ↗

October 27 Council package and supporting records ↗

October 27 recording, capital-plan approval about 28:15 ↗

Planning · Staff target

Present the updated General Plan and Zoning By-law to council.

Partial
On recordMay 26, 2026
Age at review (October 21, 2026)148 days
ResponsiblePlanning and Development
DeadlineFall 2026
What the record proves

The October 20 written update reports drafting and translation progress and gives a revised timetable. It targets draft publication for Council and public comment in December 2026, first reading in January 2027 and adoption in May 2027.

What remains

The earlier fall 2026 return target is retained for comparison. Draft publication, hearings, ministerial approval and adoption still need later evidence; the timetable is not completion.

May 26 meeting record and audio ↗

October 20 planning update and milestone table ↗

Roads · Adopted motion

Carry out the 2026 Road Improvement Project under the $6.441-million contract awarded to Pilitak Enterprises.

Partial
On recordJune 23, 2026
Age at review (October 21, 2026)120 days
ResponsibleCity Administration and contractor
DeadlineContract schedule not in registry
What the record proves

Motion 26-131 records the contract award. During the October 20 capital presentation, the CFO reported paving in Plateau and on Apex Road and described further paving in the proposed 2027 plan. This is staff-reported progress, not certification that the original contract is complete.

What remains

Match completed streets and quantities to the $6.441-million contract, including change orders and final cost. Proposed future paving is separate from acceptance of completed work.

June 23 motion registry ↗

October 20 recording, paving discussion about 50:00 ↗

Planning · Administration commitment

Bring council a request for decision and possible policy on delegating compliant annual quarry-permit renewals while preserving council oversight.

On watch
On recordJune 16, 2026
Age at review (September 16, 2026)91 days
ResponsibleCity Administration
DeadlineFall 2026
What the record proves

During the full June 16 recording, the CAO committed to returning in the fall after councillors expressed both support and concern about delegated authority.

What remains

No resulting request for decision or policy was identified in the public records indexed through August 25.

June 16 meeting record and audio ↗
Housing · Staff target

Work toward the 2027 construction season for the Tundra Ridge development, subject to required approvals.

On watch
On recordJuly 28, 2026
Age at review (September 16, 2026)49 days
ResponsibleDeveloper and City Administration
Deadline2027 construction season
What the record proves

Staff told council the selected proposal contained a detailed schedule and identified 2027 as the target season.

What remains

The public should be able to compare permits, lease execution and site work with the target as each milestone occurs.

July 28 council package ↗
Governance · Staff target

Bring the Council document-system cost into operating-budget planning and work toward implementation in early 2027.

On watch
On recordOctober 6, 2026
Age at review (October 21, 2026)15 days
ResponsibleCity Clerk and Administration
DeadlineEarly 2027 target, subject to budget and procurement
What the record proves

The October 6 memo describes software research and an expected early-2027 system. The Clerk said public documents would continue on the City website.

What remains

No selected supplier, approved price, executed contract or launch is established by the information item.

October 6 package, electronic document-sharing memo ↗
Planning · Adopted motion

Prepare correspondence for Council consideration on expediting the GN decision on the Heritage Trust land request.

Delivered
On recordOctober 6, 2026
Age at review (October 28, 2026)22 days
ResponsibleCity Administration and Council
DeadlineBefore the next Council meeting
What the record proves

The October 27 Council package contains the requested draft correspondence. In the recording Council approves the letter, with the chair announcing unanimous support. This delivers the preparation and Council-consideration commitment.

What remains

A signed, transmitted copy and GN response remain to be located. Those later steps do not undo delivery of the narrower drafting commitment. Land and construction approvals remain separate.

October 6 motion registry, GP 26-55 ↗

October 27 Council package, draft letter ↗

October 27 recording, correspondence approval about 29:25 ↗

Governance · Staff target

Review Council allowances and return for fuller discussion of the indemnity bylaw early in the new year.

On watch
On recordOctober 20, 2026
Age at review (October 21, 2026)1 days
ResponsibleCity Clerk and Administration
DeadlineEarly 2027, January suggested
What the record proves

Near the end of the October 20 recording, the chair requests an allowances review and fuller discussion early in the new year, suggesting January. The Clerk says elected-compensation changes would apply to the council elected in 2027.

What remains

A follow-up report, proposed bylaw and Council decision remain future records. No pay increase or change to the mayor’s role was approved.

October 20 recording, about 2:09:40 ↗
01

Classify the words

An adopted motion, an administration commitment and a staff target are not treated as the same thing.

02

Follow the evidence

Later minutes, registries, contracts and reports are matched back to the original commitment.

03

Show what is missing

Authorization is not completion. When the public record stops, the tracker says so plainly.