Council · Q2 2023

Council Meeting #09

May 9, 2023

Minutes audited
Attendance basisApproved minutes and registry, outgoing council. Deputy Mayor Sheppard chaired; six councillors voted until Smith left after the closed session, leaving five for motion 23-140. No conflicts were declared. This meeting is outside current-term totals.
Motions indexed138 classified substantive
Question reviewSubstantive questions appear in the written minutes; distinct count and audio review pending
Recorded present

Kyle Sheppard · Swany Amarapala · Ookalik Curley · Simon Nattaq · Kimberly Smith · Romeyn Stevenson · Samuel Tilley

Recorded absent

Solomon Awa · Paul Quassa

  1. Council met from 6 to 7:19 p.m. Motions 23-129 through 23-141 reconcile with the registry. Agenda, prior minutes, closed-session transitions and adjournment were procedural. The deputy mayor chaired without an ordinary vote.
  2. Motions 23-132 through 23-134 awarded a $216,400 plus GST snowblower supply contract and approved $153,270 plus GST for Sivumugiaq Street water-main construction support and $106,020 plus GST for ATCO Loop decommissioning support. Council also appointed a Deputy City Clerk under 23-131.
  3. Motion 23-135 to award $98,520 plus GST for Aquatic Centre sauna repairs was defeated 1–5. The minutes name Nattaq for and Amarapala, Curley, Smith, Stevenson and Tilley opposed. A defeated award is not an approved contract; the chair is not among the named voters.
  4. Motion 23-136 approved a $523,938 plus GST Apex River supplemental-pumping change order to address electrical, mechanical and construction requirements. Staff hoped to start pumping by early or mid-June, but the minutes do not establish when pumping actually began or how much water was delivered.
  5. Motion 23-137 approved $78,949.16 plus GST for additional survey fieldwork connected to the landfill road and Northwest Deposit. The minutes describe a quarry-area survey, not a completed expansion.
  6. Smith left after the closed session while attending remotely. The registry records five unanimous votes on 23-140, the $145,989.12 plus GST IT maintenance award, rather than the earlier six. Her participation is not inferred for that motion.
PRIMARY RECORD

Read the City’s documents

This page is an index, not a substitute for the underlying record.